Permit guideRichmond HillBuilding PermitsAdditions & Alterations
Addition, alteration and finished basement permits
The BCA requires that a building permit be issued before you start any work on an addition or any material alterations to an existing building.
Check whether you need a permit
- The BCA requires that a building permit be issued before you start any work on a new house, an addition or any material alterations to an existing building.
- Renovating a building, or a material alteration of a building
- An addition to a building, including sunrooms
- Altering the interior of a building, including finishing a basement
- Altering or remodelling a plumbing and/or HVAC system
- Building a fireplace and chimney
- Installing a woodstove or chimney
- During the planning phase of your project, you must determine what zoning requirements apply to your property. For all zoning and compliance-related information, visit Zoning and Compliance Letter Requests. Please note that we do not provide zoning information over the phone or in person at this time.
Projects that don't need a permitYou don't need a building permit for the following projects:
- Painting or decorating
- Installing kitchen or bathroom cupboards
- Roof shingling, unless it is a clay tile roof
- Eavestroughing
- Damp-proofing a basement
- Making minor repairs to bricks or blocks
- Projects that do not require a building permit still need to follow Richmond Hill's zoning by-laws.
Get your pre-approvals
There are a number of steps to apply for residential building permits, including pre-approvals, such as:
- Site alteration permits (approved grading)
- Planning approval (SPA), where applicable
- Conservation authority approval (TRCA)
- Urban planning approval
- Only if the addition is greater than 400 ft2 in footprint area
Additions over 400 ft2: get a site alteration permit first
- Additions greater than 400 ft2 in footprint area require a site alteration permit prior to applying for a building permit
Prepare your plans0 of 18
The Addition or Alteration checklist lists drawing types required for a complete application including: site plans, architectural drawings, mechanical drawings and structural information, etc.
You need an account to see these 18 items.It’s free. Use Sign in at the top of the page to create one, then tick the items off on any device and print them as a checklist.
Complete the forms8
Forms must be completed and signed electronically. All City of Richmond Hill Building forms are available online in fillable format.
Pre-screening
There are two steps to the online submission process: Pre-screening and Formal application.
- All types of building permits applications (residential and non-residential) can be applied for on-line. Online applications are processed and issued electronically following online payment by credit card.
- When a pre-screening submission is made, a reference number will be assigned and the Building Division will pre-screen your submission to determine if all of the submission requirements are included.
- Where it is determined that the acceptance criteria has been satisfied through the pre-screening stage, you will be advised by email from Building Division staff the requirements to move to the formal application stage, including the applicable fee based on the fee schedule.
- Where the submission is deemed to be insufficient, you will continue to coordinate with Building Division staff until such time the submission is determined to be acceptable.
- Applications for any building permit will be reviewed for completeness and you will hear from us within 2 business days.
Formal application
- Once a confirmation email is received with a list of outstanding items (including the applicable fee), you are ready to complete your application.
- Following the instructions provided, you will reply to the email with a reference to the assigned reference number and attach any outstanding PDFs as requested (if any). If no further attachment is necessary, simply advise the Building Division staff member before you make the required payment.
- A building permit fee is required to complete the application. Online applications must be paid online by credit card (Visa or Mastercard).
- Please note that the formal submission must be made and the applicable fee must be received in full within two weeks from the date in which the confirmation email is sent by the Building Division. Otherwise, the reference number will no longer be valid and you will need to resubmit all relevant files and documents.
- Payment by Visa or MasterCard is limited to a maximum of $100,000.00. Any balance of payment may be paid by cash or cheque.
- When the building permit is issued, it is the responsibility of the permit holder to print the permit card and relevant drawings/documents (in colour) and keep them on the construction site.
Pay the fee
All permit fees are due at the time of permit application. When application fees are in excess of $20,000, applicants may elect to pay 50% of the fee at the application stage and the balance at the time of permit issuance.
- $27.37 per m2 (≈ $2.54 per sq ft), building addition fee
- $10.40 per m2 (≈ $0.97 per sq ft), building alteration fee
- Fees for drains and plumbing work may also apply
- $6.56 per m2 (≈ $0.61 per sq ft)
- $210.12 flat fee (minimum residential permit fee)
- Fees for drains and plumbing work may also apply
- $158.40 minimum plumbing fee
- $47.97 flat fee for water service
- $196.61 flat fee for sanitary and storm drains
- $28.40 per fixture for additions or alteration projects only
Book your inspections
- You are responsible for notifying us when you reach each stage of the housing inspection process.
Written from Richmond Hill’s own pages as published on 19 October 2026. The municipality decides what a permit needs: confirm with it before you apply. Legal notice