Mississauga · Inspectionswritten

Building By-law Schedule "D" — Prescribed Notices / Inspections

Published by The Corporation of the City of Mississauga under Book A Building Permit Inspection

Form ref
City of Mississauga building by-law
Applies to
any
Covers label
Notices and inspections listed

Schedule "D" to The Corporation of the City of Mississauga building by-law, printed across pages 19 and 20 as a two-column table pairing each prescribed notice or inspection with a description of the construction stage it marks. The stages run from footing and backfill through framing, HVAC rough-in, insulation, fire separations, fire protection systems and fire access routes, then building sewers and drains, water service pipe, fire service main and the plumbing rough-ins, pool and spa outlets and circulation, sewage system excavation and completion, site services, occupancy stages and the four final inspections.

What it covers

  • Prescribed notices / inspections
  • Notice / Inspection
  • Description
  • Footing
  • Backfill
  • Framing
  • HVAC rough-in
  • Insulation
  • Fire separations
  • Fire protection systems
  • Fire access routes
  • Building sewers
  • Building drains
  • Water service pipe
  • Fire service main
  • Plumbing rough-in (DWV)
  • Plumbing rough-in (water distribution)
  • Pool/spa suction and gravity outlet system
  • Pool/spa circulation/ recirculation system
  • Sewage system excavation
  • Sewage system completion
  • Site services
  • Occupancy permit (unfinished building)
  • Final (plumbing)
  • Final (HVAC)
  • Final (completion of occupied building)
  • Final (general)
Check this against the municipality before you rely on it. DocHub collects what a municipality published; it cannot tell you what is in force today. A newer version may exist, may be titled differently, or may not be posted publicly at all.
Publisher
The Corporation of the City of Mississauga
Category
Inspections
Published under
Book A Building Permit Inspection — the municipality's own heading
Work types
new construction · plumbing · hvac · sewage system · swimming pool
Covers note
The schedule is a table — these are its two column headings and the notice/inspection names printed in the left column.
Instruments
City of Mississauga building by-law · Ontario Building Code, Division C, sentence 1.3.3.1.(3) · Ontario Building Code, Division A, clause 1.3.1.1.(1)(j)
Tags
inspectionsscheduleby-lawnoticesconstruction-stages
Building By-law Schedule "D" — Prescribed Notices / InspectionsOpen at mississauga.ca

Pick a document. It opens here as the real file — you can select its text, search inside it, follow its own links, and every page is present.