Schedule "D" to The Corporation of the City of Mississauga building by-law, printed across pages 19 and 20 as a two-column table pairing each prescribed notice or inspection with a description of the construction stage it marks. The stages run from footing and backfill through framing, HVAC rough-in, insulation, fire separations, fire protection systems and fire access routes, then building sewers and drains, water service pipe, fire service main and the plumbing rough-ins, pool and spa outlets and circulation, sewage system excavation and completion, site services, occupancy stages and the four final inspections.
What it covers
- Prescribed notices / inspections
- Notice / Inspection
- Description
- Footing
- Backfill
- Framing
- HVAC rough-in
- Insulation
- Fire separations
- Fire protection systems
- Fire access routes
- Building sewers
- Building drains
- Water service pipe
- Fire service main
- Plumbing rough-in (DWV)
- Plumbing rough-in (water distribution)
- Pool/spa suction and gravity outlet system
- Pool/spa circulation/ recirculation system
- Sewage system excavation
- Sewage system completion
- Site services
- Occupancy permit (unfinished building)
- Final (plumbing)
- Final (HVAC)
- Final (completion of occupied building)
- Final (general)
Check this against the municipality before you rely on it. DocHub collects what a municipality published; it cannot tell you what is in force today. A newer version may exist, may be titled differently, or may not be posted publicly at all.
- Publisher
- The Corporation of the City of Mississauga
- Category
- Inspections
- Published under
- Book A Building Permit Inspection — the municipality's own heading
- Work types
- new construction · plumbing · hvac · sewage system · swimming pool
- Covers note
- The schedule is a table — these are its two column headings and the notice/inspection names printed in the left column.
- Instruments
- City of Mississauga building by-law · Ontario Building Code, Division C, sentence 1.3.3.1.(3) · Ontario Building Code, Division A, clause 1.3.1.1.(1)(j)
- Tags
inspectionsscheduleby-lawnoticesconstruction-stages